Brockwell Lido Poolworks Update! 27th Nov.

The Lido's pool was meant to have finished repair on 6th December, but this will now take a fair bit longer. New Lido manager Clare Motton has revised the timetable. While gritblasting the pool base, the contractors H20 Servicing detected concrete had blown over a large section of the pool. This has meant need for additional works, which commenced on 22nd November. There is as yet no new updated schedule from H20 but Motton has has said that whatever happens, the poolworks will not interfere with the poolside Christmas Carols evening planned for December 19th.